NO.155 The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?

 
 
 
 

NO.156 The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It).
What is to be the MINIMUM size of the TR?

 
 
 
 

NO.157 A 3 trade size conduit is sized at

 
 
 
 

NO.158 Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect

 
 
 
 

NO.159 A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete
What should the program manager do to understand the financial environment?

 
 
 
 

NO.160 After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise’s investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program
due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?

 
 
 
 

NO.161 A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program.
What should the program manager do first?

 
 
 
 

NO.162 In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.

 
 
 
 

NO.163 Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

 
 
 
 

NO.164 A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.
What technique could the program manager use to gam more input from this project manager?

 
 
 
 

NO.165 Which two of the following items MUST be included in a detailed SoW? (Select two options.)

 
 
 
 
 

NO.166 The program manager completed the program’s benefits analysis and planning activities.
What will this ensure tor the program?

 
 
 
 

NO.167 A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability
When creating the program resource management plan, what should the program manager do first?

 
 
 
 

NO.168 What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?

 
 
 
 

NO.169 A telephone facility and an electrical facility are required in a tunnel. To reduce the effects of EMI and eliminate the need for additional shielding of the cables, where would each facility be placed?

 
 
 
 
 

NO.170 When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

 
 
 
 
 

NO.171 Stakeholders ask the program manager to assess reasons for the project’s delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget
The program manager distributes information in accordance with which of the following?

 
 
 
 

NO.172 The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?

 
 
 
 

NO.173 During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.
What should the program manager do to address the situation’?

 
 
 
 

NO.174 An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However the business team does not report to the IT program manager and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?

 
 
 
 

Get 100% Real Free BICSI Certification RCDDv15 Sample Questions: https://www.examstorrent.com/RCDDv15-exam-dumps-torrent.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt qiita.com telegra.ph telegra.ph scalar.usc.edu

admin

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below